Morocco has thrown its support behind Sila Atlantik, a project that would directly connect the kingdom to Germany through two subsea power cables stretching nearly 4,800 kilometres, according to a letter from Energy Transition Minister Leila Benali revealed on Thursday, August 20, by German business daily Handelsblatt.

In the letter, addressed to German Economy Ministry State Secretary Frank Wetzel, Benali says the Moroccan government welcomes the project, which she describes as being “fully aligned with Morocco’s strategic vision”. Rabat also says it is ready to discuss the project’s development in close coordination with the German government.

The letter comes in response to a message sent earlier this year by Wetzel, in which Berlin expressed its interest in Sila Atlantik and sought the support of the Moroccan authorities.

The project envisages the development of up to 15 GW of solar and wind capacity in Morocco, alongside battery storage. The electricity would be transmitted to Germany through two 1.8 GW subsea HVDC cables, giving the link a total capacity of 3.6 GW.

The developers are targeting annual output of up to 26 TWh, equivalent to around 5% of Germany’s electricity consumption. The two systems are due to connect to the German grid at Emden/West and Sechtem.

Disagreements emerged in July

Benali’s backing comes a month after several disagreements between the parties were made public.

Reuters reported on July 22, citing four Moroccan and German sources familiar with the matter, that the project was being held up by differences over its structure and the public guarantees underpinning it.

According to the news agency, Rabat is notably seeking a formal intergovernmental agreement with Berlin to secure long-term backing from both governments.

Morocco also wants the cables to be able to carry electricity in both directions, whereas the project was initially designed primarily to supply the German market. A bidirectional link would be technically feasible but more expensive, a German source told Reuters.

The question of land allocation also remains unresolved. As of July, Moroccan authorities had not approved the allocation of around 150,000 hectares in the Guelmim-Oued Noun region to Sila Atlantik. The land had previously been considered for Xlinks’ planned Morocco-UK power link.

The letter revealed by Handelsblatt does not indicate whether any of these three issues have since been resolved.

Commissioning envisaged for 2033

Sila Atlantik remains at a preparatory stage. No final investment decision or start of construction has been announced.

A project monitoring document published in February 2026 by the Weser-Ems regional administration lists 2033 as the envisaged commissioning date and confirms a total capacity of 3.6 GW, split between two 1.8 GW systems.

The developers estimate the total infrastructure cost at around $30 billion.

The project could become one of the world’s longest subsea electricity links. The cables would run along Europe’s Atlantic coast before reaching Germany via the North Sea.