The Ceuta migration crisis has brought Morocco’s reliance on Spanish electricity back into the debate in Spain, with some experts and media outlets pointing to the cables beneath the Strait of Gibraltar as a potential source of leverage over Rabat. The idea has drawn sharp criticism in the Moroccan press this week, although Madrid has made no official move to cut supplies.
“Morocco has a real energy dependence on Spain, particularly when it comes to electricity,” Ignacio Urbasos, a researcher at the University of Navarra, told InfoLibre on 3 August.
He estimates that 8% to 12% of the electricity consumed in Morocco currently comes from the Iberian Peninsula. Urbasos argued that this gives Madrid some leverage, while stopping short of advocating a cutoff.
The debate gained momentum on 10 August, when El Mundo asked whether the 29 kilometres of power cables beneath the strait could allow Spain to “shut down Morocco’s economy”.
Soon afterwards, Tanja24 accused Spanish media outlets of “encouraging a power cutoff to Morocco”, while Moroccan outlet Assahifa said the cables were being portrayed in the Spanish media as a potential “weapon against Morocco”.
Why these cables matter
Morocco and Spain are connected by two subsea power links, commissioned in 1997 and 2006, with a combined technical capacity of around 1,400 MW.
In 2025, Spain exported more electricity to Morocco than in any year since 2017, with net exports reaching 3,743 GWh.
Assahifa also stressed that the importance of the links goes beyond “the simple volume of energy” transmitted to Morocco.
That is because the cables do more than allow Morocco to buy Spanish electricity. They also connect the kingdom to the wider European grid. If a power plant goes offline or demand suddenly surges, Morocco can quickly draw additional electricity from across the strait to help keep its grid balanced.
A largely theoretical “weapon”
No one is currently advocating cutting off electricity to Morocco. Former Red Eléctrica chairman Luis Atienza has rejected the idea of using the cables as a pressure tactic. Former Spanish intelligence chief and ex-ambassador to Morocco Jorge Dezcallar, meanwhile, told El Mundo he would not rule out the “energy weapon”, but immediately warned of the risk of an “undesirable spiral”.
Assahifa likewise argued that a cutoff would be “an escalation measure that would also come at a high cost for Spain”, particularly for Spanish companies operating in Morocco. The links are also bidirectional: during the 28 April 2025 Iberian blackout, Morocco supplied electricity to Spain to help restore its grid.
Rabat is also seeking to expand its connections with Europe. Alongside a third link being considered with Spain, Morocco is preparing an interconnection of up to 2,000 MW with France and in July revived an older power-link project with Portugal, for which the two countries hope to secure European and private financing.
A far more ambitious project, Sila Atlantik, would also connect Morocco to Germany through subsea cables. Valued at around $30 billion, it remains stalled by disagreements over its structure and guarantees.
The controversy comes in the wake of the Ceuta migration crisis in late July, which reignited debate in Spain over relations with Rabat and the status of the enclave, administered by Madrid but claimed by Morocco.