Terna, Italy’s electricity grid operator, and STEG, Tunisia’s state-owned electricity and gas utility, have awarded Hitachi Energy a contract worth around €770 million for the converter stations of the ELMED project, La Presse de Tunisie reported in an article published on July 1.
The stations are designed to connect the Tunisian and Italian power grids through an underwater electricity link between Mlaabi, in Cape Bon, and Partanna, in Sicily. The project includes a 600 MW cable stretching around 220 km, including nearly 200 km under the Mediterranean.
ELMED will not generate electricity. The link is meant to allow power to flow between the two shores in both directions, depending on supply and demand.
Two days before the June 24 Hitachi announcement, Prysmian had received the go-ahead from Terna and STEG to build the subsea cable. The contract is estimated at around €460 million.
Already approved and financed for several years, ELMED is now moving into the phase of major technical contracts. The link is described as the first direct electricity interconnection between Europe and North Africa.
You can find our map with the drawing below :